Retrofit Instructions
From re:3D
Customers who have purchased the full Gigabot 2 to Gigabot 3 retrofit, please follow these manuals below to complete your installation:
- Side Panel Installation
- Filament Detection Installation
- Power and Z Limit Switch Relocation
- Gigabot Trolley and Cable Carrier Upgrade
Wiring diagrams are linked to at the bottom of this page
GB2 and GB3 Wheeled Platforms Wheeled Platform
Gigabot Wiring Diagrams
Note: The Filament Detection diagram shows red and black limit switch wires, but the actual wires are white and black. Until this diagram is updated, please interchange red with white.
See the visual below to determine your Azteeg version: